  2. PROGRESS REPORTS

    Manager's report, October 13.— "Main shaft sunk 4 to 93 ft.; opening out set for No. 1 level put in and shaft timbered throughout. ...

    Article : 90 words
  3. MINING

    At the Childe Harold the option holders have not made a start to date. A sampling option has been ...

    Article : 266 words
  4. LEONORA CENTRAL

    Manager's report, October 27.— The main shaft has been repaired and broken timbers replaced and is now ready for the pump. A 12 ft. ...

    Article : 58 words
  5. DE BERNALES GROUP

    The following progress reports dealing with operations on three of the de Hernales group of companies have been cabled to the head ...

    Article : 242 words
  6. GREAT NORTHERN EUREKA

    Manager's report, October 25:— Main Shaft, 45 ft. Level: North-east drive extended 8 to 14 ft., still in good values. Have arranged for a ...

    Article : 202 words
  7. MT. MARTIN GOLD MINE, N.L.

    Consulting engineer's report, October 31:— The Cornish lift pump at commencement of working functioned ...

    Article : 188 words
  8. PARINGA M. AND E. CO., LTD.

    The Paringa Mining and Exploration Co., Ltd. has issued the following circular:— The company owns a gold mining ...

    Article : 320 words
  9. LADY EVELYN G.M. N.L.

    Consulting engineer's report, October 31:— Good progress has been made with the installation of the five-head ...

    Article : 108 words
  10. NORTH-WEST G.M. CO.

    Supervisor's report, October 29:— 60 ft. Level: East crosscut advanced 8 ft., making total 26 ft. Out smallvein quartz; face now mullock. West ...

    Article : 35 words
  11. ORA BANDA SOUTH G.M.

    Consulting engineer's report October 31:— Progress has been slow on the new shaft as we are now in hard ...

    Article : 133 words
  12. MENZIES WESTRALIAN GOLD

    Manager's report, October 27:— Shaft sunk to 32 ft., in iron-stained schist of a decomposed nature. At bottom of shaft a lode formation ...

    Article : 145 words
  13. NORTH KALGURLI (1912) LTD.

    Underground manager's report for the week ended November 1:— North Kalgurli Shaft No. 8 Level: Main east crosscut ...

    Article : 499 words
  14. NEW KALGURLI GOLD MINE, N.L.

    Consulting engineer's report, October 31:—The final stages of the erection of the plant have been completed, and the plant given its ...

    Article : 125 words
  15. HANSEL MUNDY G.M. CO.

    Manager's report, October 27:— Batlow (N.S.W.) Option: The two prospectors have been loaming and boring, and have sunk a test shaft ...

    Article : 48 words
  16. MT. JACKSON NORTH GOLD MNES, N.L.

    The following telegram has been received from the company's manager. H. Oldfield:—"Ounce stone in face south drive number one shaft ...

    Article : 30 words
  17. GRANITES DEVELOPMENT N.L.

    Manager's report, October 5 :— North Wiluna: Drill hole commenced, coring 355 ft. in quartz; now casing, then recommencing ...

    Article : 26 words
  18. CARBINE GOLD MINES

    Manager's report, November 1 :— Main Shaft.—Crawford Lode, 185 ft. Level—South Drive: Values improved to 6 dwt. Ore going to battery. ...

    Article : 73 words
  19. WILUNA AJAX G.M.

    Manager's report, October 24:— Both shaft contracts signed and work started October 22. New costeen begun, buildings nearing ...

    Article : 33 words
  20. OCTOBER OUTPUTS

    The manager reports under date October 26:—"Crushed 445 tons for 167 oz. bullion, valued at 81/3 announce. ...

    Article : 25 words
×

Buy

Download

Please choose from the following download options:

Share

Share this item on:

Print

Print page as...

The National Library of Australia's Copies Direct service lets you purchase higher quality, larger sized photocopies or electronic copies of newspapers pages.

Scope
Format of download
as... PDF PDF

You need to login before you can save preferences.

$